Mynt has completed phases I and II of a three-phase project to drive this IT manufacturing facility building to net zero energy. We have begun engineering on the parking lot solar structures which will provide the remaining 1/3 of its power and complete this project (Phase III) in Q4 2017. In addition to the rooftop and carport solar (Phase II), Mynt has installed new LED lighting, new HVAC equipment, and window film. According to the Living Futures Institute, this will be the first retrofitted NZE manufacturing building in the country. When completed, this 1.02 megawatt system will generate more than 1.6 million kWh of clean power per year and over $8 Million in avoided utility costs, over the next 25 years.